Hartrick Bluff Road Improvements
Status: Final Design
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
Knob Creek Trail
Status: Final Design
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
1st Street Sidewalks
Status: Final Design
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
Apache Drive Sidewalks
Status: Construction
Expected Completion: 2023
Traffic Impacts: NA
Street Closure Map: NA
Lake Pointe Drive Extension
Status: Preliminary Design
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
North Pea Ridge
PHASE ONE
Status: Dry Utilities Relocated
Expected Completion: January 2023
Traffic Impacts: NA
Street Closure Map: NA
PHASE 2
Status: Final Design
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
Poison Oak Road Improvements
PHASE ONE
Status: Dry Utilities Relocation
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
PHASE TWO
Status: Dry Utilities Relocation
Expected Completion: 2024
Traffic Impacts: NA
Street Closure Map: NA
South 31st Street Sidewalk Project
Status: Warranty
Expected Completion: TBD
Traffic Impacts: NA
Street Closure Map: NA
Azalea Drive Improvements
Status: Construction
Expected Completion: May 2023
Traffic Impacts: NA
Street Closure Map: NA
North 42nd Street Improvements
Status: Final Design
Expected Completion: 2023
Traffic Impacts: NA
Street Closure Map: NA
South 1st Street Sidewalk Improvements from Avenue M to Avenue R
Status: Construction
Expected Completion: March 2023
Traffic Impacts: NA
Street Closure Map: NA
South Pea Ridge
Status: Dry Utilities Relocated
Expected Completion: February 2025
Traffic Impacts: NA
Street Closure Map: NA
West Central Avenue Crosswalk Improvement at South 1st Street
Status: Final Design
Expected Completion: April 2023
Traffic Impacts: NA
Street Closure Map: NA
Georgetown Railroad Trail
Status: Final Design
Expected Completion: 2023
Traffic Impacts: NA
Street Closure Map: NA
Kegley Road
Phase II
Status: A second layer of asphalt is needed. Before the second layer is finished, construction activities such as installing sidewalks and guardrails must be completed.
Expected Completion: April 7, 2023
Traffic Impacts: Kegley Road closed
Phase III & IV
Status: Not started
Expected Completion: 15-24 months after construction starts
Traffic Impacts: Kegley Road closed
Current Road Closures