Utilities Projects
Project |
Budget |
Actual Commit/Spend |
Status |
Scheduled Completion |
Charter Oak Waterline Replacement, Phase II |
5,113,045 |
4,721,270 |
Construction |
Jan-22 |
WTP Improvements - Tasks 3 - Lagoon Improvements |
4,126,987 |
426,987 |
Engineering |
Aug-22 |
Knob Creek Trunk Sewer |
2,360,794 |
2,360,793 |
Engineering |
June-21 |
TCIP - Poison Oak Utility Improvements, Phase I & II |
1,823,429 |
123,429 |
Engineering |
Dec-23 |
Temple-Belton WWTP Expansion, Phase I {Construction} |
10,358,760 |
10,355,771 |
Substantially Complete |
Apr-21 |
Bird Creek Interceptor, Phase IV (A & B) |
14,486,050 |
14,122,742 |
Construction |
Aug-22 |
New Pepper Creek Storage Tank |
3,365,803 |
3,291,522 |
Construction |
Construction |
Membrane Water Treatment Plant Expansion |
51,000,000 |
47,648,088 |
Construction |
Aug-23 |
Hartrick Ranch Wastewater CSA {Kiella Development} |
3,925,000 |
3,827,900 |
Cost Sharing Agreement Authorized |
Nov-21 |
Hartrick Bluff Water Line |
1,310,000 |
104,415 |
Engineering |
Sept-21 |
Canyon Creek / Blackland Wastewater CSA |
1,730,000 |
1,674,005 |
Cost Sharing Agreement Authorized |
Jan-22 |
Bird Creek Basin Assessment |
2,242,000 |
2,242,000 |
Substantially Complete |
Apr-21 |
920 Pressure Plane Elevated Storage Tank |
5,179,565 |
179,565 |
Engineering |
July-22 |
IH35 to Range Road & Lucius McCelvey 12" Water Line Improvements |
2,209,869 |
214,585 |
Engineering |
June-22 |
SSES - Knob Creek Assessment |
1,800,000 |
1,688,505 |
In Progress |
May-22 |
SH 317 Transmission Main (Design and ROW) |
1,300,000 |
- |
Planning |
May-22 |
*Showing projects with budget more than $1 million