Reinvestment Zone 1 Projects

Project

Budget

Actual Commit/Spend

Status

Scheduled Completion

Crossroads Park @ Pepper Creek Trail {Park Bond Funds in Project 101311}

6,823,310

6,823,310

Substantially Complete

Apr-21

Downtown - Santa Fe Plaza

14,967,409

14,870,552

Substantially Complete

Apr-21

TMED - 31st St./Loop 363 Improvements/Monumentation

1,463,637

1,013,636

Construction

Sept-21

Downtown City Center / Hawn Hotel

6,545,200

571,900

Engineering

Feb-23

Santa Fe Market Trail

5,178,384

5,158,384

Substantially Complete

Apr-21

MLK Festival Fields
(Building, Parking Lot and Electric)

2,414,900

399,207

Engineering

Dec-21

1st Street from Ave A to Central Ave

1,692,660

1,548,129

Construction

June-21

N 31st Street (Nugent to Central)

8,907,000

8,636,932

Construction

Sept-21

Corporate Hangar, Phase IV

1,732,000

479,600

Engineering

TBD

Extraco Parking Garage & Underground Electric Utilities

7,920,501

1,341,086

Engineering

June-22

Ave C - Main Street to 24th Street
{Design & ROW}

2,647,378

2,595,488

Engineering

June-21

Ave C - Main Street to MLK {Construction}

2,052,622

1,341,414

Construction

June-21

1st Street from Ave A to Ave B

1,044,598

1,019,137

Construction

June-21

Parking Garage @ 4th Street and Central Ave

11,851,100

1,144,449

Engineering

June-22

Adams/Central Ave - Bicycle & Pedestrian Improvements

1,690,448

1,103,843

In Progress

Nov-21


*Showing projects with budget more than $1 million