Mobility Projects
Project |
Budget |
Actual Commit/Spend |
Status |
Scheduled Completion |
Outer Loop, Phase IIIB |
5,804,538 |
5,804,538 |
Construction |
May-21 |
Prairie View Road, Phase II |
9,398,215 |
9,398,215 |
Construction |
June-21 |
Kegley Road, Phase II |
8,013,800 |
2,222,102 |
Engineering |
July-22 |
N Pea Ridge, Phase I |
2,185,000 |
999,244 |
Engineering |
Sept-21 |
Outer Loop West, Phase I |
3,213,330 |
2,532,544 |
Engineering |
May-21 |
Poison Oak, Phase I & II |
15,005,000 |
3,974,913 |
Engineering |
Dec-23 |
South Pea Ridge Road |
1,375,000 |
640,930 |
Engineering |
Aug-22 |
Azalea Drive - 31st Street to Lowes Drive |
1,442,800 |
102,800 |
On Hold |
TBD |
Canyon Creek / Blackland Road Extension |
1,215,270 |
1,052,698 |
Engineering |
Feb-22 |
Hartrick Bluff Road Reconstruction {Design Only} |
1,376,825 |
1,059,933 |
Engineering |
June-21 |
Azalea Drive Phase II & III CSA {Patco Construction, LLC} |
3,400,000 |
3,356,905 |
Construction |
Apr-22 |
*Showing projects with budget more than $1 million